Purchase requisition vs material request: in D365 F&O, a purchase requisition asks to buy from an external vendor and leads to a purchase order. A material request asks the warehouse to issue stock you already own and should lead to an inventory journal. Treating them as the same process is a common cause of poor site adoption.
Purchase requisition vs material request: two different jobs
One assumption comes up in almost every D365 F&O project for a project business: “We have purchase requisitions, so material requests are covered.” They aren’t.
The two processes serve different purposes, suit different people and lead to different transactions. When one has to do the other’s job, operations stops using the system.
What a purchase requisition is for
A purchase requisition in D365 is an internal request to buy something from a vendor. Once approved, it becomes a purchase order.
It’s built for procurement. It works with vendor catalogs, procurement categories, spending limits and approval hierarchies based on who can commit the company to external spend. For that job, it works well.
What a material request is for
A site material request asks the warehouse to issue materials the business already owns. Nobody needs to buy anything. The site engineer needs the stock moved to the project, charged to the right project, by a certain date.
This is an internal stock movement, not a purchase. Still, it needs the same control as any external purchase: approval, cost allocation and an audit trail.
Side-by-side comparison
| Purchase requisition | Material request | |
|---|---|---|
| Purpose | Buy from an external vendor | Issue stock from your own warehouse |
| Typical user | Procurement and admin staff | Site engineers and field teams |
| Result | Purchase order to a vendor | Inventory movement or project item journal |
| Stock | Not yet in inventory | Already in the warehouse |
| Approval logic | Spending limits and procurement policy | Project, site and priority |
| Speed expected | Days are acceptable | Often same day |
Where the two processes differ in practice
The form
The requisition form includes procurement categories, vendor suggestions and purchasing policy fields. A site engineer requesting cable ties and conduit doesn’t need any of them. A material request form needs only the site, warehouse, required date, items, quantities, priority and project.
The item list
Requisitions open the full item master and vendor catalogs. Site teams work better with a short list of items flagged for site requests, so they’re not scrolling through thousands of products.
The approval workflow
Requisition workflows follow procurement policy, such as spending limits and department hierarchy. Site requests need routing by project and priority instead. A request for materials needed tomorrow can’t wait three days in an approver’s queue.
Budget control
Both can use D365 budget control. D365 checks a requisition as a purchase commitment. A material request, instead, should go through a check against the project budget on submission, which is the moment stock issued from your own warehouse is usually not checked at all.
What happens after approval
This is the biggest difference. An approved requisition leads to a purchase order and a goods receipt. There is no standard path from an approved requisition to an internal inventory journal.
So, when teams use requisitions for site requests, the warehouse has to create the inventory journal by hand, as a separate step, with no link to the request. That manual step is where most errors start: late journals, wrong quantities and wrong project codes.
Financial dimensions and the audit trail
On a requisition, dimensions flow to the purchase order and the invoice. With a material request process, they should flow from the request straight into the journal, so nobody re-enters them. In addition, the journal should keep a reference to the request, so the chain from request to ledger entry can be traced both ways.
Visibility across sites
Requisition views serve procurement: by vendor, category and policy. Operations managers need a different view: all open requests by site, project and status. That view is what reveals duplicate requests and surplus stock.
When to use each one
Use a purchase requisition when:
- The items must be bought from a vendor
- The result should be a purchase order
- The user works in procurement or administration
- Approval follows spending limits and procurement policy
Use a material request when:
- The items are already in your warehouse
- The result should be an internal inventory movement
- The user is a site engineer, foreman or project team member
- Approval follows the project and the priority
The two are not competing. They’re complementary processes for different jobs, and project businesses need both.
Why the workarounds don't hold
Some teams use requisitions anyway, sometimes with dummy vendors or manual journals. Others skip the request and let the warehouse post journals directly. Both approaches fail in predictable ways.
With requisitions, the process is too slow for site teams, so they go back to WhatsApp and email. With direct journals, stock moves without a request, an approval or a budget check, so you get the transaction but lose the control.
The fix is a dedicated request step between the site and the warehouse. We describe the full process in our guide to site material requests in D365.
How SysMaterialRequest handles the second flow
SysMaterialRequest adds the material request to D365 F&O and leaves your purchase requisitions as they are. It provides:
- A short request form with a curated item list
- A budget check on submission, with warn, block or override options
- D365 workflow approval by project and priority
- One-click issue that creates the inventory movement or project item journal, with the dimensions filled in
- One list of all requests across sites and statuses
Frequently asked questions
Can we use purchase requisitions for internal material requests?
Technically yes, but it creates problems. The requisition leads to a purchase order, not an inventory journal, so the warehouse has to bridge the gap manually. Site teams also find the form too slow and go back to informal channels.
Do material requests replace purchase requisitions?
No. Requisitions remain the right tool for buying from vendors. A material request covers the internal issue of stock you already own. Most project businesses need both.
Can a material request be checked against the project budget?
Yes. With D365 budget control, the system checks the request value against the project budget on submission, before any stock moves. You decide whether an overrun warns, blocks or needs an override.
What happens if the warehouse can't issue everything?
In a good process, the storekeeper issues what’s available and the rest stays open on the same request. In SysMaterialRequest, the storekeeper issues the remaining quantity when stock arrives.